Notice from ABCi: Documents required for "Form C" applications

Photo credit: ABCi
Categories: Contract, Management & Professional Practice
April 08, 2019

With regards to this matter, please be notified that starting from 01 April, 2019, should there be applications for the BA - Deviation to the Approved Plan, the relevant QP / TP parties need to present the Development Approval Form (Form C), through the Onebiz system before the renovations are carried out on the site.

The documents required for the Development Approval Form (Form C) are as such:-

  • The latest Form C

  • Structural Drawings (if relevant)

Note: If the structural drawings are UNNEEDED for the renovation plan, please present a cover letter for notification.

As a reminder, the QP/TP parties need to ensure that the constructors appointed by the owner/developer possess the right business category and valid certification under the Ministry of Development.

 

For Land Works, the constructor is required to have business category KA01.

For Building Works, the constructor is required to have business category B01.

For Water Meter Installations, the constructor is required to have business category KPB04.

 

DEALING CONTROL DIVISION

Building Control and Construction Control Authority (ABCi)

Ministry of Development


..............................................................................................................................................................................................................................................................


Sehubungan dengan ini, adalah dimaklumkan bahawa mulai 01 April, 2019, jika terdapat permohonan Perubahan Kepada Pelan Yang Telah Diluluskan (BA-Deviation to the Approved Plan), pihak QP/TP hendaklah menghadapkan permohonan Kebenaran Memulakan Kemajuan (Boran C) melalui sistem Onebiz sebelum perubahan tersebut dilaksanakan di tapak.


Dokumen-dokumen yang diperlukan bagi permohonan Kebenaran Memulakan Kemajuan (Borang C) adalah seperti berikut:-

  • Borang C yang terkini
  • Structural Drawings (jika berkenaan)

Nota: Jika Structural Drawings TIDAK diperlukan bagi perubahan pelan, sila hadapkan surat (cover letter) untuk makluman.


Sebagai peringatan, pihak QP/TP hendaklah memastikan pembina yang dilantik oleh Pemilik/Pemaju mempunyai kategori kerja yang bersesuaian dan pendaftaran yang sah di Kementerian Pembangunan.


Bagi Kerja-Kerja Tanah, Pembina hendaklah mempunyai kategori kerja KA01.

Bagi Kerja-Kerja Pembangunan, Pembina hendaklah mempunyai kategori kerja B01.

Bagi Kerja-Kerja Pemasangan Meter Air, Pembina hendaklah mempunyai kategori kerja KPB04.


BAHAGIAN KAWALAN KEMAJUAN

Authoriti Kawalan Bangunan dan Industri Pembinaan (ABCi)

Kementerian Pembangunan